Regarding the reporting regime on implementation progress of real estate projects
Circular No. 11/1013/TT-BXD dated July 31, 2013 of the Ministry os Construction prescribing the reporting regime on implementation of investment in construction and business in real estate projects
Posted: 12/8/2013 8:46:05 AM | Latest updated: 16/7/2019 11:36:09 AM (GMT+7) | Newsletter #:3298
Effective: 1-Oct-2013
Status: Expired on: 15-Aug-2019
This Circular guides the implementation of reports on carrying out investment in construction and business in real estate projects, include:• Projects on housing development;
• Projects on investment in construction of new urban centers;
• Projects on mixed apartment buildings;
• Projects on technical infrastructure of industrial zones;
• Projects on shopping mall, offices for rent, hotels;
• Projects on ecological and convalescence tourist zones.
Contents and time limits for reports are provided in Article 4, as follow:
• General report on basic information of real estate projects (in accordance with the Form provided at Annex 6); the time limit is 7 days after having the decision on permission of investment
• Report on carrying out investment in construction of projects such as land clearance, investment in construction of technical infrastructure works; (Form at Annex 7). The Time limit for sending quarterly report is before the 25th day of end month of quarter; for annual reports is before December 25 of each year
• Report on business status at project such as status of mobilizing capital (Form at Annex 8); status of performing financial obligations (Form at Annex 9); status of selling the houses, leasing house, transferring land use rights, leasing land... (Form at Annex 10). The time limit for sending the report is similar to the report on carrying out investment in construction
• Report on ending investment in construction of projects (Form at Annex 11), the report must be sent 15 days after finishing investment in construction of works according to investment stages or finishing sub-projects and 15 days after finishing investment in construction of entire works of projects.
The above reports must be sent to the Ministry of Construction (at the address of The Department of House and Real Estate Market Management, number 37 Le Dai Hanh, Ha Noi) and the provincial Construction Departments where have projects.
The reporting regime prescribed in this Circular shall be applied from Quarter IV/2013.
For projects which are being implemented: The time limit for sending report is within 30 days after this Circular takes effect (October 1, 2013)
For projects which have been finished and accepted for receipt and putting into use from January 01, 2013 to October 1, 2013, is only submitted the report on ending investment in construction of projects (the Form at Annex 11)
Effective notes
- The contents about general report on basic information of real estate project, report on carrying out investment in construction of projects regulated at points a and b Clause 2 Article 4 of this Circular and the contents about report on status of selling the houses, leasing house, transferring land use rights, leasing land...regulated at point c Clause 2 Article 4 of this Circular shall be expired from February 1st, 2017. See the new regulations at Circular No. 27/2016/TT-BXD dated December 15th, 2016.
- This Circular shall be annulled from August 15th, 2019, according to the regulations at Circular No. 01/2019/TT-BXD dated June 28th, 2019.