Procedures for approving the design and licensing of construction of intersections connecting to local roads in Ho Chi Minh City
Decision No. 37/2026/QD-UBND dated June 18, 2026 of the People's Committee of Ho Chi Minh City stipulating the order and procedures for approving the design and the order and procedures for licensing the construction of intersections for local roads being exploited in Ho Chi Minh City (15 pages)
Posted: 23/6/2026 3:39:10 PM | Latest updated: 24/6/2026 9:40:07 AM (GMT+7)
Effective: 1-Jul-2026
Status: No amendments
This decision replaces 02 procedures including design approval and construction permit for intersections connecting to local roads being exploited in Ho Chi Minh City. The detailed content is as follows:
1. Procedures for approving the design of intersections connecting to local roads being exploited:
• Subjects: The investor of the project to build an intersection connecting to the local road being exploited.
• Content:
◦ Dossier of application: Includes application, investment policy, intersection design, report on verification results (if any), dossier of capacity of design/verification organization, detailed design dossier (explanation, nature, drawings, cost estimates, technical instructions, maintenance process).
◦ Contents of the design dossier: Must show the location, scale, measures to ensure traffic safety, assessment of the impact on traffic order and safety, determination of location, type of intersection, scale of branch roads, traffic organization plan, construction works, relocation, etc compensation and reimbursement of infrastructure.
◦ Order and time limit for settlement: Receive, examine the dossier, notify additional (if missing), check and issue a written approval (within 07 working days from the receipt of a complete dossier).
◦ Validity period: The design approval document is valid for 24 months. If this time limit is exceeded or there is a change in the scale, the procedure must be redone.
• Authority:
◦ Department of Construction: Approve the design of works connected to roads managed by the Departments, simultaneously connected to roads managed by the Departments and commune-level People's Committees, connected to investment roads under PPP, connected to regional roads in project areas that have been completed but not yet handed over.
◦ Commune-level People's Committees: Approve designs for works connected to roads managed by commune-level People's Committees (except for cases of provincial-level Construction Departments), connected to internal roads in project areas that have been completed but not yet handed over.
2. Procedures for licensing the construction of intersections connecting to local roads being exploited:
• Subjects: The investor of the project to build an intersection connecting to the local road being exploited.
• Content:
◦ Application dossier: Includes an application, explanation and drawings of measures to organize construction, measures to ensure traffic during construction.
◦ Order and time limit for settlement: Receiving, examining dossiers, additional notices (if missing), reviewing dossiers and issuing construction permits (within 05 working days from the receipt of complete dossiers).
◦ Validity period: The construction permit has a term according to the approved construction schedule. If the time limit has not been completed, the licensing procedures must be redone.
• Authority: Similar to the design approval authority (Department of Construction or commune-level People's Committee).
To annul the Decision No. 07/2025/QD-UBND dated February 06, 2025 of the People's Committee of Ba Ria - Vung Tau province on the order and procedures for approving the design and the order and procedures for licensing the construction of intersections for local roads being exploited in Ba Ria - Vung Tau province.
The Decision takes effect from July 1, 2026.