The new provision on adjustment of construction contract prices
Circular No. 07/2016/TT-BXD dated March 10th, 2016 of the Ministry of Construction on guiding the adjustment of construction contract prices
Posted: 1/4/2016 11:07:49 AM | Latest updated: 6/3/2023 10:09:24 AM (GMT+7) | Newsletter #:3944
Effective: 1-May-2016
Status: Expired on: 20-Apr-2023
This Circular guides the adjustment of construction contract prices, covering: principles of price adjustment, cases eligible for price adjustment, order of and procedures for, and contents and methods of, adjusting construction contract pricesAccordingly, one of the new points of this Circular is the supplement of the provisions on which the adjustment of construction contract prices is not permitted in these cases (Clauses 4 and 5 of Article 2)
• The contract value corresponding to the advance payment level exceeding the minimum advance level specified in Clause 5, Article 18 of Decree No. 37/2015/ND-CP⛔
• Additional work volumes arising due to the contractor’s subjective fault
• Those of the compensation responsibility of insurers
In addition, for a package contract, a fixed unit price-based contract, according to the new provisions, the contract price adjustment may only be made with regard to force majeure events specified in Clause 2, Article 51 of Decree No. 37/2015/ND-CP⛔ or other force majeure circumstances (such as karst caves, mud layers, antiques, archaeological relics encountered or found in the construction process) which cannot be anticipated by the parties when entering into the contract (Clause 1 and Clause 2 Article 3)
This Circular takes effect from May 01st, 2016 and replaces Circular No. 08/2010/TT-BXD⛔ dated July 29th, 2010.
Effective notes
This Circular shall be expired from April 20th, 2023, replaced by Circular No. 02/2023/TT-BXD dated March 3rd, 2023.