It is required to apply for a license for any solar power project having a capacity of at least 1 MW
Circular No. 16/2017/TT-BCT dated September 12th, 2017 of the Ministry of Industry and Trade on project development and model Power Purchase Agreements applied to solar power projects
Posted: 13/9/2017 10:59:10 AM | Latest updated: 28/7/2020 9:02:41 AM (GMT+7) | Newsletter #:4306
Effective: 26-Oct-2017
Status: Expired on: 31-Aug-2020
According to Article 13 of this Circular, grid-connected PV power project or rooftop PV power project having a capacity of 1 (one) MW or over must obtain the license for generating electricity and comply with the Circular No. 12/2017/TT-BCT⛔ .In addition, power purchase agreements applied to solar power projects must follow the model power purchase agreements issued in Annexes 2 and 3 of this Circular.
This Circular takes effect from October 26th, 2017.
The seller and the buyer shall negotiate and conclude an appendix of revisions specified in this Circular as from June 1st, 2017 in case of a solar power project that has been operated prior to June 1st, 2017.
The solar power project having a commercial operation date from June 1st, 2017 to the effective date of this Circular shall be executed according to the specimen power purchase agreements from the day on which the project is put into commercial operation.
Effective notes
- See more the amendments, supplements at Circular No. 05/2019/TT-BCT⛔ dated March 11th, 2019.
- This Circular shall be expired from August 31st, 2020, replaced by Circular No. 18/2020/TT-BCT
dated July 17th, 2020.