Circular No. 10/2026/TT-BNV dated May 28, 2026 of the Ministry of Home Affairs stipulating the decentralization of authority of the Minister of Home Affairs to manage in the fields of budget, public assets, construction investment and investment in information technology application (13 pages)
Posted: 29/5/2026 10:53:27 AM | Latest updated: 30/5/2026 3:50:02 AM (GMT+7)
Effective: 1-Jun-2026
Status: No amendments
The following are the management contents in the field of budget, public assets, construction investment and investment in information technology application that have been delegated by the Ministry of Home Affairs:
Article 4. Decentralization of authority in budget management
1. Head of level-II estimating unit: Decision on approval/adjustment of tasks and estimates from recurrent expenditures (non-autonomous assignment) with a total budget of over 0.5 billion VND/task.
2. Heads of budget-using units:
a) Decision on approval/adjustment of tasks and estimates from recurrent expenditures (assigned involuntarily) with a total budget of up to 0.5 billion VND/task.
b) Decide on approval/adjustment of tasks and estimates from lawful funding sources.
Article 5. Decentralization of the competence to decide on procurement, repair, renovation and upgrading of assets and equipment; rental of goods and services
1. Heads of level-II estimating units: Decision on approval of guidelines and estimated funding:
a) From state budget recurrent expenditures: over VND 0.5 billion to VND 02 billion/task.
b) From lawful funding sources: over VND 01 billion to VND 03 billion/task.
2. Heads of budget-using units: Decision on approval of guidelines and estimated funding:
a) From state budget recurrent expenditures: up to 0.5 billion VND/task.
b) From lawful funding sources: to 01 billion VND/task.
Article 6. Decentralization of authority to decide on the task of repairing, renovating, upgrading, expanding and building new work items
1. Heads of level-II estimating units: Decisions approving guidelines, economic-technical reports, settlements:
a) From state budget recurrent expenditures: over VND 01 billion to VND 03 billion/task.
b) From lawful funding sources: over VND 02 billion to VND 05 billion/task.
2. Heads of budget-using units: Decisions approving guidelines, economic-technical reports, settlements:
a) From state budget recurrent expenditures: up to 01 billion VND/task.
b) From lawful funding sources: to 02 billion VND/task.
Article 7. Decentralization of authority in construction investment management
• Heads of level-II estimating units: Decision/adjustment/suspension of investment policies; decision/adjustment of the project; finalization of group-C investment projects using public investment capital from lawful funding sources.
Article 8. Decentralization of authority in the management of investment in information technology application
1. Heads of level-II estimating units:
a) Deciding/adjusting investment policies, projects and settlement of group-C IT projects from lawful funding sources.
b) Approving the policy and estimated funding for IT tasks from the state budget recurrent expenditure: over VND 0.5 billion to VND 02 billion/task.
c) Approve the policy and estimated funding for IT tasks from lawful funding sources: over VND 01 billion to VND 03 billion/task.
2. Heads of budget-using units:
a) Approve the estimate of preparation for investment in IT tasks using recurrent expenditure funds with a total estimate of less than VND 20 billion.
b) Approve the policy and estimated funding for IT tasks from the state budget recurrent expenditure: up to VND 0.5 billion/task.
c) Approve the policy and estimated funding for IT tasks from lawful funding sources: up to 01 billion VND/task.
Article 9. Decentralization of authority in the management and use of public property
1. Heads of level-II estimating units:
a) Transfer of assets (except for houses, land, cars) between units.
b) Fixed funds for the use of machinery and equipment (except for automobiles).
c) Adjust the price of machinery and equipment from over 15% to not more than 30% higher than the regulations.
d) Selling assets with historical costs of between VND 0.25 billion and less than VND 2 billion/unit or revaluation value of between VND 50 million and VND 200 million/unit.
dd) Liquidate assets with historical costs of between VND 0.5 billion and less than VND 2 billion/unit or revaluation value of between VND 50 million and VND 200 million/unit.
e) Handling of assets (recovered, destroyed, lost or destroyed) with a historical cost of less than VND 2 billion/unit or a revaluation value of up to VND 200 million/unit.
g) Approve the list, standards and norms of special-use assets with a historical cost of VND 100 million or more/unit.
h) Exploitation of public property in service of auxiliary activities.
i) Exploitation of assets being historical-cultural relics.
2. Heads of budget-using units:
a) Selling assets with a historical cost of less than VND 0.25 billion/unit or a revaluation value of less than VND 50 million/unit.
b) Liquidation of assets with historical cost of less than VND 0.5 billion/unit or revaluation value of less than VND 50 million/unit.
c) Approve the list, standards and norms of special-use assets with a historical cost of less than VND 100 million/unit.
d) Establishing the ownership of the whole people and approving the plan for handling the property voluntarily transferred by the owner.
dd) Prescribe regimes, standards and norms for maintenance and repair of assets.