blue-check Ninh Thuan nuclear power plant's compensation and resettlement part is separated into an independent project. English attachment

Resolution No. 66.8/2025/NQ-CP dated November 26, 2025 of the Government on separating the compensation, support and resettlement contents of the nuclear power project for which the National Assembly has decided on investment policy into an independent project (4 pages)
Posted: 28/11/2025 8:56:29 AM | Latest updated: 7/12/2025 5:00:40 PM (GMT+7)
Effective: 26-Nov-2025 Status: No amendments
This Resolution focuses on separating the compensation, support and resettlement contents of the Ninh Thuan nuclear power project into an independent project (Article 1.1). This is to resolve difficulties and problems related to this work.
Subjects of application of the Resolution include Khanh Hoa province, investors, units preparing the Ninh Thuan nuclear power project and related organizations and individuals (Article 1.2). This clearly defines the scope of responsibilities and rights of each party.
The People's Committee of Khanh Hoa province is assigned to be the governing body of the Project, and at the same time the Chairman of the Provincial People's Committee has the right to decide on project investment while waiting for the adjustment of the investment policy and approval of adjustments to the nuclear power project (Article 2.2). This gives great autonomy to the locality in implementing the compensation, support and resettlement project.
During the time waiting for resettlement, people whose land is recovered will be supported with temporary housing or rent, with the support level prescribed by the People's Committee of Khanh Hoa province (Article 2.3). This ensures the right to housing for people during the project implementation.
The Project implementation is applied in the form of shortened bidding procedure for consulting and non-consulting packages (Article 2.5). This speeds up the progress of contractor selection and project implementation.
The land recovery process is regulated in detail, ensuring transparency and compliance with the law (Article 2.6). Land users are responsible for coordinating with the unit implementing compensation, support and resettlement.
Funds for project implementation are taken from the central budget, increased revenue, expenditure savings, central budget reserves and other legal sources of capital (Article 3). This ensures financial resources for project implementation.
The Resolution takes effect from the date of signing and promulgation until February 28, 2027.
The implementation of the previous resettlement and migration project under Decision No. 794/QD-TTg of the Prime Minister stopped (Article 5.1).
 