New regulations on revenues and expenditures for projects funded by the state budget
Circular No. 79/2026/TT-BTC dated July 1, 2026 of the Ministry of Finance regulating revenues and expenditures of investors and project management boards with projects funded by the state budget (34 pages)
Posted: 7/7/2026 9:26:52 AM | Latest updated: 9/7/2026 2:16:25 PM (GMT+7)
Effective: 1-Jul-2026
Status: No amendments
The following are important changes in revenues and expenditures of projects using state capital under this Circular:
1. Scope of regulation and subjects of application:
• Scope: This Circular details revenues and expenditures of investors and project management boards (PMUs) for projects funded by the state budget.
• Subjects: Applicable to investors, PMUs established by investors, PMUs established by authorized representatives of agencies, organizations and enterprises, and PMUs being public non-business units.
• ODA and concessional loans: Projects using ODA and foreign concessional loans will manage revenues and expenditures in accordance with international treaties, signed loan/aid agreements and current laws. If there are no separate regulations, this Circular shall apply.
• Encouraging application: Investors and PMUs not using state budget capital are encouraged to apply the provisions of this Circular to manage projects.
2. Revenue source and revenue distribution:
• Revenue sources include:
◦ Revenues from project expenses: Includes deducted project management expenses and other revenue sources from the project (except for compensation, support and resettlement expenses).
◦ Other lawful revenues: Revenues from consultancy activities for other projects and other lawful revenues.
◦ State budget allocation (if any).
• Distribution of revenues between the investor and the PMU: The head of the unit acting as the investor shall decide in writing the ratio of project management revenue between the investor and the PMU based on the content, workload and responsibilities of each party.
3. Trading Account:
• For revenues from projects, charges, fees and state budget revenues: The investor and the PMU shall open an account at the State Treasury for management.
• For other revenue sources, the fund shall be set aside: Investors and PMUs may open deposit accounts at the State Treasury or commercial banks.
4. Classification of Project Management Unit:
• Group I: Includes the investor organizing the implementation of project management, the PMU established by the investor, the PMU established by the competent representative of the agency, organization or enterprise (except for the PMU which is a public non-business unit).
• Group II: Includes public non-business units established according to regulations.
5. Estimating revenues and expenditures:
• Basis for estimation: Decision on establishment of PMU, decision on approval of investment policy, project, estimate, regulations on cost deduction, internal expenditure regulations, salary calculation table, etc.
• Making revenue estimates: Including the revenues specified in Article 2. The revenue from the cost of each project is determined based on project management costs and consultancy costs performed by the PMU, or outsourcing costs.
• Annual revenue and expenditure estimates: The investor decides to make 01 general estimate or 02 separate estimates for the investor and the PMU. The expenditure estimate of the Investor and the PMU includes the cost of investment supervision and assessment.
6. Appraisal and approval of annual estimates:
• Authority: Depends on the type of agency or unit as the investor (administrative agency, enterprise, or other units).
• Application dossier: Includes relevant approval decisions, cost calculation sheets, payroll tables, revenue and expenditure estimates.
• Appraisal contents: Appraisal of work contents, calculation methods, standards, norms, conformity of cost allocation, conformity with the state financial regime.
• Time limit: Maximum 10 working days for appraisal, no later than 31/12 of the previous year for approval of the plan year estimate.
• Adjustment of estimates: Group I PMUs may actively adjust expenditures between expenditure contents within the approved estimate. In case the revenue does not meet the estimate, the expenditure must be adjusted accordingly. If the revenue or expenditure estimate is exceeded, it is necessary to appraise and approve the adjustment.
7. Annual settlement of revenues and expenditures:
• Preparation of settlement reports: Group I PMUs shall make revenue and expenditure settlement reports no later than 28/02 of the following year.
• Competence to verify and approve: Similar to the competence to appraise and approve estimates. For administrative agencies, the investor shall draft a decision on approval and collect opinions from the unit with the function of financial management before promulgating it.
• Allocation of costs for projects: For PMUs managing 02 or more projects, costs shall be allocated directly or proportionally corresponding to the value of the task volume of each project.
• Verification contents: Verifying the use of revenues, the conformity between the data proposed for settlement with norms, regimes and estimates, the legality and validity of revenues and expenditures, and the suitability of the allocation of settlement value to projects.
• Difference in revenue sources: The difference in revenue sources for settlement is greater than the expenses transferred to expenditures in the following years.
• Settlement of self-implementation expenses: The settled expenses do not exceed the approved costs in the total investment or estimate of the project.
8. Project Management Boards Group II (Public Non-business Units):
• Revenue sources and assignment of financial autonomy: Includes the revenue sources specified in Article 2, in which revenues from project costs and consultancy activities are the sources of determining the level of financial autonomy.
• Formulation and implementation of estimates: Comply with the provisions of the law on the state budget and the financial autonomy mechanism of public non-business units. The revenues that have not been used up in the year shall be carried forward to the following year.
• Annual settlement of revenues and expenditures: Group II PMUs shall make reports on settlement of revenues and expenditures and send them to the finance agencies of the same level for verification and approval.
9. Responsibilities of relevant units:
• Investor, Group I PMU: Take full responsibility for the management, use of revenues, expenditures, development of internal expenditure regulations, accuracy, legality and validity of documents.
• Directors of Group II PMUs: Taking full responsibility for the management, use of revenues and expenditures, making, appraising, approving estimates, settlements, and taking responsibility for decisions in the exercise of financial autonomy.
• Payment agency: Payment at the request of the investor, PMU and comparison and confirmation of data.
• Ministries, central and local agencies: Approve the financial autonomy plan, inspect the management and use of revenues and expenditures.
• Financial agencies at all levels: Inspect, guide, handle errors and violations, give opinions on the settlement of the Group I PMU and verify and approve the settlement of the Group II PMU.
The Circular takes effect from July 1, 2026. Circular No. 70/2024/TT-BTC⛔ dated 01/10/2024 is annulled.