Limits and regulations must know within the

Circular No. 12/2025/TT-BCT⚠️ - New regulations on determining electricity price and model power purchase agreement

Effective date: 01-Feb-2025
Limitations
◦ Maximum internal rate of return (Article 3.1.b). The power purchase contract price shall not be based on a financial internal rate of return (IRR) exceeding 12%.
◦ Electricity price compared to the electricity generation price framework (Article 3.4). The electricity purchase and sale contract price of the base year must not exceed the electricity generation price framework issued by the Minister of Industry and Trade in the base year. In case the base year does not have an electricity generation price framework, the electricity purchase and sale contract price must be converted to compare with the nearest electricity generation price framework after the base year of that type of power plant.
◦ Minimum equity ratio (Article 5.2.d). The minimum equity ratio is 15% of the total project investment.
◦ Adjustment of operating and maintenance prices according to maximum labor costs (Article 17.1.b). The component of operating and maintenance prices according to labor costs is adjusted according to fluctuations in the regional minimum wage or according to the CPI index announced by the Central Statistics Office but not exceeding 2.5%/year.
### Need to know
◦ Scope of regulation (Article 1.1). This Circular provides detailed guidance on the method of determining electricity generation service prices; principles of calculating electricity prices to implement power projects; main contents of power purchase contracts.
◦ Subjects of application (Article 1.2). This Circular applies to power plants connected to the national power system and other relevant agencies, organizations and individuals.
◦ Not applicable subjects (Article 1.3). The Circular does not apply to multi-purpose strategic hydropower plants, small renewable energy plants applying the avoided cost pricing mechanism, independent power plants invested in the form of BOT, power plants and generators providing ancillary services; power plants applying the electricity purchase price mechanism in documents of competent authorities.
◦ Principles for determining electricity generation service prices (Article 3.1). The electricity purchase and sale contract price is built on the basis of reasonable and valid expenses of the investor during the entire economic life of the project.
◦ Price components not included (Article 3.3). The electricity purchase and sale contract price does not include value added tax, water resource tax, water resource exploitation right fee, forest environmental service fee, environmental protection fee for solid waste and industrial wastewater (applicable to thermal power plants) and other taxes, fees, and other cash receipts as prescribed by competent state management agencies (except for taxes and fees already calculated in the electricity generation service price plan).
◦ Power purchase contract price and power generation price framework (Article 3.4). The power purchase contract price of the base year must be compared with the power generation price framework issued by the Minister of Industry and Trade in the base year, in which the power purchase contract price of the power plant to be compared with the power generation price framework is calculated on the basis of cost components corresponding to the cost components of the power generation price framework calculation.
◦ Main input parameters for calculating fixed prices (Article 5.2). Main input parameters include: investment costs, economic life, average electricity generation over many years, depreciation period, equity/loan ratio, loan interest rate/debt repayment period, and corporate income tax rate.
◦ Loan interest rate when negotiating electricity price (Article 5.2.e). Loan interest rate and loan repayment period during operation period are determined based on loan contract and documents between the investor and credit institutions. In case the total loan capital is lower than the total loan capital in the electricity price calculation plan, the remaining loan capital is agreed upon with a minimum repayment period of 10 years and interest rate according to regulations.
◦ Temporary price (Article 9). In case the price of the electricity purchase contract has not been agreed upon, the electricity seller and the electricity buyer have the right to agree on a temporary price.
◦ Principles for determining prices in bidding to select investors (Article 11). In case of organizing bidding to select investors for power projects according to the provisions of Clause 1, Article 19 of the Electricity Law, the electricity price in the bidding documents is built according to the principles in Chapter II of this Circular.
◦ Re-negotiation of electricity generation service price (Article 26). The electricity seller and the electricity buyer shall re-negotiate the electricity generation service price in the signed electricity purchase contract according to the provisions of Clause 4, Article 52 of the Electricity Law.
◦ Recalculating the price of electricity generation services according to the final investment capital (Articles 27.1, 27.2). Power plants that have signed electricity purchase and sale contracts according to the method prescribed in Circular No. 57/2020/TT-BCT, Circular No. 56/2014/TT-BCT, Circular No. 51/2015/TT-BCT and new power projects started before September 19, 2017, when having final investment capital, the electricity seller and the electricity buyer have the right to request to recalculate the price of electricity generation services according to the approved final investment capital. For power plants that have signed electricity purchase and sale contracts according to the method prescribed in Circular No. 41/2010/TT-BCT, when there is an opinion from a competent state agency on renegotiating electricity prices according to the final settlement capital, the electricity seller and the electricity buyer shall recalculate the electricity generation service price according to the approved final settlement investment capital.