Criteria for selection and guidance on making of feasibility study report on PPP project
Circular No. 02/2016/TT-BKHDT⛔ dated March 01st, 2016 of the Ministry of Planning and Investment guidance on premilinary project selection, establishment, appraisal and approval for project proposal, and feasibility study report on investment project under form of public-private partnership
Posted: 7/3/2016 9:26:44 AM | Latest updated: 18/1/2019 8:00:03 AM (GMT+7) | Newsletter #:3926
Effective: 18-Apr-2016
Status: Expired on: 15-Feb-2019
Under Article 3 of this Circular, the preliminary selection of projects on infrastructure, provision of equipment or services which are invested in the form of public-private partnership (PPP) is based on these criteria:• The project must be in conformity with sector and regional development planning and plans, and local socio-economic development plans;
• The project must be in conformity with the investment sectors defined in Article 4 of the Decree No. 15/2015/ND-CP⛔ and prioritized by the Ministry, Ministerial-level agencies or provincial people’s committees;
• The project must generate revenue to return investment capital to the investors. The project that directly generates revenue from its business operations shall be prioritized
In addition to such criteria, the preliminary selection may base on the following supplemental criteria: the consideration of investors, the project has huge demand for services, convenient factors for performing the investment (such as the site clearance has been finished; the construction of auxiliary works and connection works has been finished; it’s easy to acquire raw materials, fuels, machines and technologies on the market), etc.
This Circular takes effect from April 18th, 2016.
These Annexes are attached to this Circular:
1. Annex I: Guidance on establishment of PPP project proposal
2. Annex II: Guidance on appraisal of PPP project proposal
3. Annex III: Guidance on establishment of feasibility study report on PPP project;
4. Annex IV: Guidance on appraisal of feasibility study report on PPP project.
Effective notes
This Circular shall be expired from February 15th, 2019, replaced by Circular No. 09/2018/TT-BKHDT dated December 28th, 2018.